Temporary Road Closure at Clyne
Temporary road closure of the B4434 at the Railway Bridge, Clyne to enable Network Rail to install new strengthening plates.
The closure will be between the hours of 10.00pm and 6.00am from 3 July to 15 July 2023
Temporary road closure of the B4434 at the Railway Bridge, Clyne to enable Network Rail to install new strengthening plates.
The closure will be between the hours of 10.00pm and 6.00am from 3 July to 15 July 2023
Scheduled carriageway resurfacing works at Commercial Road, Resolven commencing Monday 12th June for 2 nights (6pm – 12am).
The scheme dates may be subject to slight change, depending on weather conditions and/or any unforeseen plant breakdowns.
Commercial Road will be closed from the A465 Roundabout to the junction with Ynysfach Avenue, with 2 way traffic lights on that junction. There will be no access to Commercial Road from John Street or Company Street.
Access to Resolven Village at the above times will be via the B4434 Clyne/Melincourt as shown in blue on the maps below.
~ ~ ~ ~